Follow Along with the Powell Hall Expansion and Renovation

May 7, 2024

Over the past two months, the south side of Powell Hall has seen a dramatic change as crews have formed and poured concrete for the SLSO’s new lobby and guest services expansion, which provide much-needed amenities to improve the visitor experience. Last week, forming continued on the fourth and final floor of the expansion that will connect to the existing Grand Circle level. Once finished, the new lobby will connect to the existing auditorium on all four levels, as well as provide more restrooms, concession areas, a coat check, a new Box Office, and additional space to gather before and after concerts.

The new lobby—designed by Snøhetta with construction management by BSI Constructors—connects to the auditorium at locations previously used as emergency exits.